Exterior Painting Bids: Weather and Substrate Scope

Write exterior painting bids with substrate notes, prep limits, product-specific weather windows, repair boundaries, lead-safe scope, and finish acceptance.

Article

The quote says:

Pressure wash, scrape loose paint, spot-prime, and apply two coats to the exterior. Five working days.

The crew sees a different job.

The west elevation is chalky. Porch trim is peeling to bare wood. One sill is soft. A downspout has been leaking onto the siding. The detached garage is aluminum, not wood. Afternoon storms are in the forecast, and the customer thinks a low rain percentage means the paint schedule is guaranteed.

The price may still be good. The paperwork is not.

An exterior painting bid has to define three things before the first drop cloth comes off the truck:

  1. What material is under the coating and what condition it is in.
  2. What preparation and coating system the price includes.
  3. What field conditions create a workable painting window.

Miss any one of those and “two coats” can turn into unpaid carpentry, moisture troubleshooting, extra mobilizations, failed adhesion, or an argument over why the crew stopped at noon.

If the takeoff itself is still hiding labor, start with Painting Bids by the Square Foot: When It Works and When It Lies. This article takes the next step: turning the exterior conditions around that takeoff into an approved field scope.

Use the painting forms catalog as one connected job file. The painting quote establishes the price, the painting bid and scope attachment define the surfaces and system, the painting work order carries the stop-work rules into the field, and the painting inspection report records conditions and closeout.

Build an elevation schedule before you price

“Paint house exterior” is not a measurable scope.

Label the work so the estimator, crew, and customer can point to the same place:

  • E-01 — front/east elevation;
  • E-02 — right/south elevation;
  • E-03 — rear/west elevation;
  • E-04 — left/north elevation;
  • T-01 — front porch trim and columns;
  • D-01 — detached garage; and
  • X-01 — deck railing, priced as an alternate.

Then give every location a short substrate record—a note about the material receiving the coating:

FieldWhat belongs in the bid file
SurfaceSiding, trim, soffit, fascia, door, window, shutter, railing, masonry, stucco, metal, or other listed component.
SubstrateWood, engineered wood, fiber cement, vinyl, aluminum, steel, brick, concrete, stucco, or unknown beneath an existing coating.
Existing coatingIntact, chalking, faded, peeling, blistered, cracked, alligatoring, rusting, stained, patched, or unknown.
Visible conditionSound, weathered, wet-looking, soft, split, spalled, efflorescent, corroded, dented, warped, or damaged.
Included prepWashing method, scraping, sanding, feathering, patching, caulk, spot primer, full primer, rust treatment, or test area.
Repair boundaryIncluded minor repair, allowance, customer repair, specialist review, or excluded work requiring approval.
AccessGrade, roofline, porch, landscaping, power lines, driveway, lift route, scaffold area, ladder footing, and occupied openings.
EvidencePhoto numbers, measurements, moisture reading if taken, adhesion or chalk test if performed, and customer-provided records.

Start with a real site-visit estimate checklist, not a drive-by square-foot guess. The estimator should separate four categories:

  • Observed: visible peeling at T-01, open joint at E-03, rust at garage fasteners.
  • Measured or tested: dimensions, readings, or test results with the tool, location, and method recorded.
  • Reported or assumed: customer says the siding was installed in 2016; price assumes the prior coating is compatible.
  • Not inspected: concealed sheathing, wall-cavity moisture, inaccessible upper trim, coating chemistry, structural condition, and hazardous-material status unless separately established.

That distinction keeps a visual estimate from pretending to be an engineering, moisture, lead, or building-envelope investigation.

Price the substrate, not just the square footage

The same gallon does not turn every exterior into the same job.

Substrate or assemblyConditions to record before selecting the system
Wood siding and trimBare areas, peeling depth, checking, open end grain, knots or tannin staining, failed joints, soft or rotten sections, fastener staining, splashback, roof/gutter leaks, and surface moisture where relevant.
Engineered wood or fiber cementEdge condition, impact damage, failed joints, exposed substrate, factory finish if known, chalking, moisture exposure, and manufacturer-specific repair or coating requirements.
Stucco, concrete, and masonryCracks, spalls, powdering, efflorescence, prior coating, repairs, cure history if new, water entry, grade contact, and whether a specialty sealer, filler, or primer is required.
Vinyl or aluminum sidingChalking or oxidation, dents, buckling, loose panels, sealant condition, original and selected color, manufacturer restrictions, and whether the selected coating permits the proposed color and substrate.
Steel and ferrous metalRust grade, bare metal, mill scale if applicable, failed coating edges, fasteners, water traps, contamination, and the exact rust-prep and primer system.
Mixed exteriorTransitions among siding, trim, masonry, metal, sealants, flashings, doors, windows, railings, and customer-excluded components.

The U.S. Forest Service's Wood Handbook chapter on finishing wood treats water, sunlight, weathering, wood properties, and moisture control as central to exterior finish performance. The National Park Service's Preservation Brief 10 on exterior paint problems makes the field consequence plain: repainting before a moisture source is corrected can lead to another failure.

That does not make the painter responsible for diagnosing every leak. It means the bid should not promise that paint will cure a wet assembly.

Write the boundary:

Visual review found peeling and dark staining at rear elevation E-03 below the upper gutter return. Base price includes coating removal to the next sound layer, feather sanding, and spot priming after the listed substrate is dry and ready for the selected system. Locating or repairing roof, gutter, flashing, wall-cavity, plumbing, or drainage moisture sources is excluded. If the affected substrate does not reach the coating manufacturer's application requirements, work at E-03 will pause pending correction and written approval of any added repair or return visit.

The hidden-conditions workflow is the right continuation when scraping exposes rot, failed sheathing, incompatible layers, or a larger repair than the bid included.

“Prep included” is not a scope

Customers hear “prep included” and picture every defect disappearing.

The estimator may mean one wash and a quick scrape.

PCA Standard P14, Levels of Surface Preparation for Repainting and Maintenance Projects Receiving Architectural Coatings, connects preparation level to both appearance and cost. It also separates ordinary repaint preparation from restoration and resurfacing.

You do not need to copy a whole standard into a residential bid. You do need to convert the chosen result into crew-readable limits:

Prep itemDefine it before approval
WashingLow-pressure rinse, detergent wash, hand cleaning, mildew treatment, pressure washing, rinse water controls, and required dry time.
Loose coatingWhich elevations, removal to what stopping point, and whether full stripping is excluded.
SandingFeather-edge only, profile reduction, full smoothing, mechanical method, dust control, and lead-safe restrictions where applicable.
PatchingMaterial, locations, size/count allowance, texture/profile limitation, and whether substrate replacement is excluded.
Caulk or sealantListed joints only, product type, maximum gap, removal of failed material, tooling, cure time, and exclusions for glazing or building-envelope sealants.
PrimerSpot or full prime, exact product or approved equal, bare areas, stains, tannins, rust, masonry, adhesion, and compatible temperature range.
RepairsIncluded linear feet or unit allowance, unit price, separate alternate, or written change before repair.
ProtectionPlants, roofs, paving, windows, fixtures, vehicles, neighboring property, occupants, and daily cleanup.

A useful scope does not say “scrape as needed.” It says what the price buys:

Base preparation at E-01 through E-04 includes detergent cleaning and rinse, removal of visibly loose and peeling coating to the next sound edge, feather sanding of prepared edges, spot priming of bare listed substrate, and replacement of up to 40 linear feet of failed painter's caulk at identified trim-to-siding joints. Full paint removal, skim coating, siding replacement, carpentry, glazing, sealant-joint design, moisture-source correction, masonry crack repair, rust-through repair, and concealed damage are excluded unless listed as an alternate or approved change.

If the customer wants a lower price, reduce a visible scope item or offer an alternate. Do not leave the same promised finish attached to a hidden reduction in prep.

Name the coating system

“Premium exterior paint” is not a specification.

At minimum, the approved bid should identify:

  • manufacturer and product line, or a tightly defined approved-equal process;
  • base and color where those affect product selection;
  • sheen;
  • substrate and locations;
  • cleaner or treatment where specified;
  • patch, caulk, or repair product where it affects the system;
  • primer by substrate and condition;
  • finish coat count;
  • target application or coverage requirements when the specification uses them;
  • current technical data sheet and label governing application;
  • color restrictions on heat-sensitive substrates;
  • expected dry and recoat logic;
  • manufacturer warranty handoff; and
  • contractor workmanship warranty and exclusions as a separate promise.

The technical data sheet is not a brochure footnote. It is part of the field plan.

The limits differ even among familiar exterior products. Benjamin Moore's current Aura Exterior Satin N631 technical data sheet lists a surface-temperature application range, explains that cool or humid conditions extend dry and recoat times, and gives different preparation or primer directions for wood, masonry, vinyl, and metals. Sherwin-Williams' November 2024 Duration Exterior Acrylic Satin product data sheet adds product-specific dew-point, rain, low-temperature, recoat, direct-sun, masonry, and metal-siding limits. Behr's PRO e600 Exterior product guidance uses another temperature range and another rain, snow, or heavy-dew window.

Those examples are not interchangeable specifications. They prove why the bid should never rely on one shop-wide sentence such as “paint above 35°F.”

The selected primer can have a narrower application range than the finish. The metal elevation can have a different limit than the wood siding. A dark color on vinyl can have restrictions that the same product does not have on masonry. A cool morning can change recoat time even if application is allowed.

Use a product schedule:

AreaSubstratePrep systemPrimerFinishCoatsGoverning document
E-01 to E-04Previously painted wood sidingListed wash, scrape, feather, spot repairProduct A at bare areasProduct B, color and sheen listedListed coat countCurrent Product A and B data sheets and labels
T-01Bare and previously painted wood trimAdded edge and end-grain prepProduct CProduct BListed coat countCurrent Product B and C documents
D-01Chalking aluminum sidingClean, rinse, dry, compatibility prepAs required by selected systemProduct DListed coat countCurrent Product D data sheet and siding restrictions

Put the same schedule on the painting work order. If the office approves Product B but the crew buys a different line, the crew cannot rely on Product B's weather limits or warranty language.

A weather window uses three different records

Exterior crews often mix up climate, forecast, and field conditions.

They answer different questions:

RecordWhat it can tell youWhat it cannot promise
Historical climateTypical seasonal temperature, precipitation, wind, and working patterns for rough estimating and calendar planning.The conditions on a specific future workday.
Current forecastThe expected temperature, precipitation probability, humidity, wind, and hazards for scheduling and daily reassessment.That the job site or coating surface will stay inside the product limits.
Field conditionsThe actual air, surface, substrate, and work-area conditions when the crew is deciding whether to wash, prep, prime, coat, or stop.How conditions will change after the crew leaves unless the forecast and product window are also considered.

NOAA Climate Data Online provides historical daily, monthly, seasonal, and annual weather data. Use that for estimating patterns, not as tomorrow's forecast.

The National Weather Service defines probability of precipitation as the probability that precipitation will be reported at a certain location during a specified period. A 30% value is not a coating approval. It does not tell the crew whether a west wall is dry, whether dew will form before the film is ready, or whether the selected product's rain window will be met.

The NWS definition of dew point also matters because dew point describes atmospheric moisture and saturation, while the product sheet may require a specific separation between surface temperature and dew point. Do not guess that relationship from relative humidity alone when the selected system requires an actual check.

Keep a daily conditions log:

  • date, job, crew, and elevation or component;
  • forecast source, issue time, and period reviewed;
  • precipitation, dew, wind, heat, or other relevant forecast concern;
  • product, batch or container reference where useful, color, and coat;
  • air temperature;
  • surface temperature at the actual work area when required;
  • relative humidity and dew point when required by the product or shop procedure;
  • surface or substrate moisture observation and instrument reading when relevant, including location and tool;
  • whether washing, rain, dew, shade, direct sun, condensation, or irrigation affected the surface;
  • start, recoat, stop, and restart times;
  • photos or instrument display references; and
  • the person who made the go, move, or hold decision.

Do not create readings you did not take. “Surface dry to touch at 9:15 a.m.; no instrument reading taken” is more defensible than a fictional moisture percentage.

Write a weather-delay clause the customer can understand

“Weather permitting” is too thin by itself.

The bid should explain:

  1. which product documents control;
  2. which field conditions can stop or move the work;
  3. whether the schedule uses workable days;
  4. how the customer will be notified;
  5. what happens to unpainted, prepared, or partially coated areas;
  6. whether ordinary weather remobilization is included; and
  7. which unusual protection, standby, acceleration, or repeated remobilization costs require a written change.

Example:

Exterior coating work will proceed only when the selected primer, finish, and repair products can be applied and cured within their current label and technical-data requirements and when site access is safe. Rain, dew, condensation, wet substrate, temperature, surface temperature, humidity, wind, direct sun, heat, or other conditions may change the daily sequence or create a weather hold. Completion is estimated in workable painting days, not guaranteed consecutive calendar days. Contractor will document material conditions and schedule effects and issue a written schedule update when the stated completion range is no longer reliable. Added scope, customer-caused access delays, requested acceleration, or protection beyond the accepted scope requires written approval before added charges.

That clause is not permission to disappear for two weeks. It creates a notice duty.

Use a schedule change notice when the original window is no longer reliable. State the affected elevations, condition, work completed, protection left in place, earliest restart condition, and next update time. If the customer requests added enclosure, overtime, a different product, a larger crew, or extra repair to recover the date, use a change order before the added work.

State law can make the date language more than a customer-service choice. New York General Business Law § 771 requires approximate or estimated start and substantial-completion dates plus contingencies that would materially change the estimated completion date in covered home-improvement contracts. California Business and Professions Code § 7159 uses approximate start and completion dates and a signed written-change framework for covered contracts.

Those are state examples, not a national contract form. Verify the rule where the job sits.

Price the work that weather adds

Weather affects more than brush time.

The estimate may need to carry:

  • wash-to-dry separation before coating;
  • morning or shaded-elevation sequencing;
  • added masking or protection against drift and overspray;
  • plant and pavement protection that must be removed or reset daily;
  • scaffold, lift, or equipment days;
  • repeated setup and cleanup;
  • shorter application windows;
  • longer recoat intervals;
  • return trips for doors, shutters, trim, or final touch-up;
  • material storage limits;
  • daily inspection and documentation time; and
  • schedule slack around known seasonal patterns.

Decide what the base price includes.

For example:

Price includes normal daily setup and weather-driven resequencing among listed elevations during the estimated work period. Price excludes temporary enclosure, heating, cooling, dehumidification, special ventilation, requested overtime, standby outside normal crew policy, or repeated remobilization caused by unavailable customer access. Those items will be proposed before use.

Do not invent a “weather fee” on the final invoice. Disclose the cost rule before the customer approves the bid.

Keep repair approvals separate from painting

Exterior prep exposes things.

The crew may find:

  • rotten trim behind a peeling edge;
  • failed glazing;
  • open siding joints;
  • loose fiber-cement boards;
  • rust-through beneath a blister;
  • cracked or spalling masonry;
  • insect damage;
  • failed flashing;
  • soft sheathing;
  • a wet wall below a window;
  • incompatible old coating layers; or
  • a repair that requires another licensed trade.

Put a stop-and-price rule on the work order:

If preparation exposes unsound substrate, active moisture, concealed deterioration, failed attachment, suspected hazardous material, or repair beyond the listed allowance, stop work at the affected area. Photograph and label the condition, protect the area as authorized, notify the customer, and obtain an approved change order or specialist direction before covering or repairing it.

The photo requirements workflow is especially useful here. Require an arrival overview, close condition photo, prepared edge, repair exposure, primer, each completed elevation, and any weather or access exception. A photo of a moisture meter without an elevation label and contact location is not much of a record.

Treat lead-safe work as its own scope

Exterior scraping and sanding are often where the scope changes most.

EPA's RRP firm-certification guidance says firms, including sole proprietorships, working for compensation on covered pre-1978 housing or child-occupied facilities must meet the program's certification requirements. The federal RRP work-practice standard at 40 CFR 745.85 includes exterior containment, prohibited or restricted paint-removal practices, waste handling, cleanup, and visual inspection requirements.

The bid intake should ask:

  • building construction year and basis for that answer;
  • whether housing or a child-occupied facility is involved;
  • affected painted components;
  • planned scraping, sanding, drilling, demolition, repair, or replacement;
  • lead test or inspection records, if any;
  • whether EPA or an authorized state, tribe, or territory runs the applicable program;
  • the certified firm and certified renovator responsible for the work;
  • containment limits, adjacent property, doors, windows, ground, and landscaping;
  • cleaning, waste, and recordkeeping scope; and
  • what happens if the original price assumed non-covered work.

Do not bury covered lead-safe work in “standard prep.” Do not promise that an exemption applies from a phone description. Do not use the contract to waive a safety or regulatory duty.

Worker protection is a separate boundary. EPA RRP requirements for occupants and the work area do not replace OSHA obligations, including the construction lead standard at 29 CFR 1926.62 where it applies.

Access and heat belong in the bid

Exterior access is not free because the paint quantity is small.

OSHA's construction ladder rule at 29 CFR 1926.1053 includes stable placement, intended use, inspection, traffic-area protection, climbing, and electrical-contact requirements. OSHA's heat-exposure guidance calls for heat-illness prevention planning as part of the employer's safety program.

The estimator should record:

  • height and reach by elevation;
  • roof, porch, canopy, awning, and grade interfaces;
  • ladder footing and tie-off or access constraints;
  • scaffold or lift needs;
  • lift delivery and travel path;
  • overhead electrical exposure;
  • traffic, doors, driveways, pedestrians, tenants, and pets;
  • hot surfaces and sun exposure by time of day;
  • shade, water, breaks, and acclimatization planning;
  • wind and overspray exposure; and
  • whether access equipment remains on site during a weather hold.

Then price the method. A two-story gable that requires a lift is not a ladder allowance with optimistic wording.

Use the shop's safety process and a job-specific hazard review. The bid should name the access system included. Keep the crew's safety plan in the shop's safety process, not in an optimistic price assumption.

Define finish acceptance before the final walk

Customers may expect paint to repair shape, straighten siding, close every crack, or make old texture look new.

PCA Standard P1, included in the PCA Industry Standards collection, ties a properly painted surface to the contract documents, the manufacturer's technical data sheets, and a uniform finished appearance. That makes the accepted scope and product system part of the quality definition.

Write the finish review around:

  • approved color and sheen;
  • elevations and components included;
  • prep level and repair allowance;
  • sample or mockup approval where useful;
  • specified coat system;
  • normal viewing position and lighting;
  • known substrate profile, dents, waves, checks, patches, and prior-layer texture that may remain visible;
  • touch-up method and reasonable color and sheen limitations;
  • damage by other trades or the customer;
  • unpainted excluded surfaces;
  • cleanup and overspray standard;
  • open punch items; and
  • contractor workmanship warranty versus manufacturer product warranty.

Do not say “lifetime paint warranty” unless the actual warranty supports the promise you are making. Manufacturer warranties can limit the remedy, depend on preparation and application, and exclude labor. Hand the customer the actual product documents and write your own workmanship coverage separately.

Use a completion sign-off that identifies accepted elevations, punch items, excluded repairs, care instructions, retained product labels or color records, and the date the workmanship warranty begins.

A compact bid block the crew can actually use

Here is the center of a practical exterior painting bid:

  • Areas: E-01 through E-04 wood siding and listed trim; front door excluded; detached aluminum garage priced as Alternate 1.
  • Observed basis: visual, non-destructive review on [site-visit date]; photos P-01 through P-26; peeling at porch trim; chalking at west siding; dark staining below rear gutter; upper dormer trim viewed from grade only.
  • Prep: detergent wash and rinse; dry before coating; remove visibly loose coating to next sound edge; feather prepared edges; spot-prime bare listed substrate; replace up to 40 linear feet of failed painter's caulk at marked joints.
  • Repairs: includes two listed trim patches under 12 inches each. Rot, siding or sheathing replacement, glazing, masonry repair, active moisture correction, flashing, gutters, and concealed damage excluded pending written change.
  • System: products, colors, sheens, substrates, primers, and coat counts shown in Product Schedule PS-01. Current labels and technical data sheets govern application and recoat conditions. Substitutions require written approval.
  • Weather: estimated six workable painting days. Crew will record relevant forecast and field conditions. Work may move or pause for rain, dew, wet substrate, temperature, surface temperature, humidity, wind, direct sun, heat, unsafe access, or product cure limits. Written schedule update follows if the completion range becomes unreliable.
  • Lead: the bid is based on the lead and RRP conditions documented in Lead Record LR-01. Do not disturb affected paint until the applicable determination, responsibilities, and required work practices are confirmed. If that basis changes, stop and revise the scope and price before disturbing paint.
  • Acceptance: selected surfaces will be reviewed against the approved colors, sheen, prep level, product schedule, and listed exclusions. Existing substrate profile and excluded defects may remain visible.

That block is not the whole contract. It is the field-ready summary that connects the accepted price to what happens outside.

Final check before sending the bid

Before the customer signs, confirm:

  1. Every elevation and component is included, excluded, or priced as an alternate.
  2. Substrates and visible coating conditions are recorded by location.
  3. Measurements say how they were obtained.
  4. Prep has a method and limit.
  5. Repairs have an allowance, unit price, alternate, or stop-and-change rule.
  6. Moisture clues and unresolved water sources are visible in the scope.
  7. The exact coating system or approved-equal process is named.
  8. Primer and finish technical sheets are compatible with the proposed conditions.
  9. Weather uses workable conditions and a notice process, not a vague excuse.
  10. Access equipment, heat, wind, traffic, and adjacent-property protection are priced.
  11. Pre-1978 and lead-safe questions were handled before disturbance.
  12. Colors, sheen, sample approval, and finish expectations are written.
  13. Product and workmanship warranties are separate.
  14. The work order, daily record, change order, invoice, and completion sign-off can carry the same location labels.

An exterior painting bid should let the customer see what they are buying and let the crew know when to proceed, move, document, or stop.

That is a much stronger promise than “two coats, weather permitting.”

Sources

The regulatory pages, statutes, standards, and manufacturer documents below were checked on July 19, 2026. Product limits can change; use the current container label and technical data sheet for the product actually purchased.

This article is for general information, not legal, safety, or compliance advice. Verify licensing, lead-safe, worker-safety, contract, and product requirements for the job's state, locality, and coating system before bidding or starting work.

Common questions

Should an exterior painting bid include a weather-delay clause?
Yes. The clause should identify product-specific application and cure requirements, relevant field conditions, workable-day scheduling, customer notice, protection of incomplete work, and when added protection or remobilization needs a written change. “Weather permitting” alone does not explain the process.
What temperature is safe for exterior painting?
There is no single temperature for every exterior system. Use the current label and technical data sheet for the selected primer, finish, substrate, color, and application. Check air, surface, material, dew-point, precipitation, humidity, and recoat requirements where the product documents call for them.
Does a low rain percentage mean it is safe to paint?
No. National Weather Service precipitation probability describes the chance of precipitation at a location during a stated period. It does not establish surface dryness, dew risk, cure time, or compliance with a coating's rain window. Use the forecast for planning and actual site conditions plus the product documents for the field decision.
What substrate notes belong in an exterior paint estimate?
Record the material, existing coating condition, peeling or chalking, bare areas, moisture clues, cracks or rot, repairs, access, prior coating information if known, photos, tests or readings actually performed, and conditions not inspected. Label the notes by elevation or component.
Should a painter take moisture readings before bidding?
Take and record them when the substrate, coating system, visible condition, or shop procedure makes them relevant and the estimator has an appropriate tool and method. Identify the tool, location, date, and reading. A moisture reading does not by itself diagnose the source of water or prove concealed assemblies are dry.
Is pressure washing automatically part of exterior paint prep?
No. Define the cleaning method, pressure or non-pressure approach, detergent or treatment, protection, rinse, how runoff will be handled, and the required dry time. Some fragile, deteriorated, lead-painted, or otherwise sensitive surfaces need a different method.
What should happen when scraping exposes rot?
Stop at the affected area, photograph and label the condition, protect it as authorized, notify the customer, and use the bid's repair allowance or obtain an approved change order. Do not cover unsound substrate or expand into unapproved carpentry.
Does exterior repainting on a pre-1978 home require EPA RRP compliance?
Often, but not automatically. The federal EPA contractor guidance generally covers paid work that disturbs paint in pre-1978 housing or child-occupied facilities. It lists a minor-repair exception for 20 square feet or less of exterior paint disturbance, but window replacement and demolition of painted surfaces remain covered regardless of area, and prohibited practices remain prohibited regardless of the disturbed area. Acceptable documentation that the affected paint is lead-free can change federal coverage. Where a state, tribe, or territory administers an authorized program, check that program's requirements before pricing or disturbing paint.
How should exterior paint finish acceptance be written?
Tie acceptance to the approved elevations, color, sheen, prep level, repair limits, coating system, technical data sheets, samples where used, normal viewing conditions, cleanup, and listed pre-existing defects or substrate profile that may remain visible. If the contract uses PCA Standard P1, name the standard and its viewing setup—including finished lighting and a normal viewing position at least 39 inches away—instead of relying on a vague “looks good” test.